LoginFor the displayed Eliminated/ Downgraded investment, the summary below provides last reported snapshot of the particular investment in IT Dashboard. This summary displays a chart reflecting Overall Rating over time, clearly identifying specific activities such as rebaseline events and last reported cost and schedule ratings and Evaluation by Agency CIO. A tabular history of major events is also available at the bottom of the page.
Rated Date | Overall Rating | Cost Rating | Schedule Rating | CIO Evaluation |
---|---|---|---|---|
2009-06-30 | 7 | 4 | 10 | |
2009-08-01 | 6.3 | 4 | 10 | 3 |
2009-09-01 | 6.3 | 4 | 10 | 3 |
2009-10-01 | 6.3 | 4 | 10 | 3 |
2009-11-01 | 6.3 | 4 | 10 | 3 |
2009-12-01 | 6.3 | 4 | 10 | 3 |
2010-01-01 | 6.3 | 4 | 10 | 3 |
2010-02-01 | 6.3 | 4 | 10 | 3 |
2010-03-01 | 6.3 | 4 | 10 | 3 |
2010-03-29 | 5 | 9 | 10 | 3 |
2010-04-01 | 5 | 9 | 10 | 3 |
2010-04-30 | 2.5 | 9 | 10 | 2 |
2010-05-01 | 2.5 | 9 | 10 | 2 |
2010-06-01 | 3.5 | 2.3 | 5.7 | 2 |
2010-06-28 | 4.8 | 2.9 | 6.4 | 3 |
2010-07-01 | 4.7 | 2.9 | 6.4 | 3 |
2010-07-29 | 5 | 3.4 | 6.7 | 3 |
2010-08-01 | 5 | 3.4 | 6.6 | 3 |
2010-08-30 | 5.5 | 4.6 | 7 | 3 |
2010-08-31 | 5 | 5.5 | 8.4 | 3 |
2010-09-01 | 5.2 | 3.5 | 7 | 3 |
2010-10-01 | 5 | 5.5 | 8.1 | 3 |
2010-10-28 | 5.1 | 1.6 | 8.6 | 3 |
2010-11-01 | 5 | 1.6 | 8.6 | 3 |
2010-11-30 | 5 | 7.1 | 9.9 | 3 |
2010-12-01 | 5 | 7.1 | 9.9 | 3 |
2010-12-30 | 2.5 | 8.6 | 10 | 2 |
2011-01-01 | 2.5 | 8.6 | 10 | 2 |
2011-01-28 | 5 | 8.7 | 10 | 3 |
2011-02-01 | 5 | 8.7 | 10 | 3 |
2011-02-24 | 5 | 8.6 | 9.7 | 3 |
2011-02-27 | 5 | 10 | 10 | 3 |
2011-03-01 | 5 | 10 | 10 | 3 |
2011-03-31 | 5 | 10 | 10 | 3 |
2011-04-01 | 5 | 10 | 10 | 3 |
2011-05-01 | 5 | 8.4 | 9.8 | 3 |
2011-05-26 | 5 | 8.6 | 9.9 | 3 |
2011-05-27 | 5 | 8.6 | 9.9 | 3 |
2011-06-01 | 5 | 8.6 | 9.8 | 3 |
2011-07-01 | 5 | 9.8 | 10 | 3 |
2011-07-28 | 7.5 | 10 | 10 | 4 |
2011-08-01 | 7.5 | 10 | 10 | 4 |
2011-09-01 | 7.5 | 10 | 10 | 4 |
2011-09-06 | 7.5 | 10 | 10 | 4 |
Baseline Event # | Baseline Event Date | Planned Completion Date | Life cycle costs of Approved Baseline | Reason | Comment |
---|---|---|---|---|---|
3171 | 12/27/2010 | 03/29/2013 | 57.50 | Rebaseline - other | Technical clean up in order to be able to submit to the ITDB without validation errors. Not an "official" Department approved rebaseline. |
1078 | 08/31/2010 | 03/29/2013 | 52.28 | External - Direct Mandate | Other- Required for the ITDB submission. |
6738 | 07/25/2011 | 03/29/2013 | 39.93 | Rebaseline - change in funding strategy | Administrator technical rebaseline in order to successfully submit to the ITDB. NG |
6110 | 05/27/2011 | 03/29/2013 | 59.04 | Replan - planned change with minimal change in overall scope, cost or schedule objectives | Replan to correct performance metric ITDB validation errors |
6088 | 05/20/2011 | 03/29/2013 | 59.04 | Replan - planned change with minimal change in overall scope, cost or schedule objectives | Update to performance metrics. |
3859 | 03/31/2011 | 03/29/2013 | 59.04 | Rebaseline - other | Rebaselined to address ITDB submission issues. |
3862 | 03/31/2011 | 03/29/2013 | 59.04 | Rebaseline - other | Rebaselined to address ITDB submission issues. |
3549 | 02/27/2011 | 03/29/2013 | 59.04 | Correction | Minor corrections to address ITDB submission errors. |