LoginFor the displayed Eliminated/ Downgraded investment, the summary below provides last reported snapshot of the particular investment in IT Dashboard. This summary displays a chart reflecting Overall Rating over time, clearly identifying specific activities such as rebaseline events and last reported cost and schedule ratings and Evaluation by Agency CIO. A tabular history of major events is also available at the bottom of the page.
Rated Date | Overall Rating | Cost Rating | Schedule Rating | CIO Evaluation |
---|---|---|---|---|
2010-03-16 | 7.5 | 10 | 10 | 4 |
2010-05-01 | 7.5 | 10 | 10 | 4 |
2010-06-01 | 2.8 | 1 | 4 | |
2010-06-14 | 4.7 | 0.7 | 6 | 4 |
2010-07-01 | 4.6 | 0.7 | 5.6 | 4 |
2010-07-23 | 5 | 2 | 5.4 | 4 |
2010-08-01 | 4.9 | 2 | 5.2 | 4 |
2010-08-11 | 7.5 | 9.3 | 9 | 4 |
2010-09-01 | 7.5 | 9.3 | 9 | 4 |
2010-10-01 | 7.5 | 9.4 | 9.4 | 4 |
2010-10-28 | 7.5 | 9.4 | 7.6 | 4 |
2010-11-01 | 7.5 | 9.4 | 7.6 | 4 |
2010-12-01 | 7.5 | 9.4 | 7.6 | 4 |
2010-12-20 | 5 | 9.4 | 7.9 | 3 |
2011-01-01 | 5 | 9.4 | 7.9 | 3 |
2011-02-01 | 5 | 9 | 9.7 | 3 |
2011-02-28 | 5 | 9.7 | 9.3 | 3 |
2011-03-01 | 5 | 9.7 | 9.3 | 3 |
2011-03-23 | 5 | 9.7 | 9.3 | 3 |
2011-04-01 | 5 | 9.7 | 9.3 | 3 |
2011-05-01 | 4.4 | 1.2 | 6.9 | 3 |
2011-06-01 | 5 | 7.3 | 8 | 3 |
2011-06-22 | 5 | 8.4 | 8.9 | 3 |
2011-07-01 | 5 | 8.4 | 8.8 | 3 |
2011-07-27 | 7.5 | 8.4 | 9.4 | 4 |
2011-08-01 | 7.5 | 8.4 | 9.3 | 4 |
2011-09-01 | 7.5 | 8.4 | 9.3 | 4 |
2011-09-06 | 7.5 | 8.4 | 9.3 | 4 |
Baseline Event # | Baseline Event Date | Planned Completion Date | Life cycle costs of Approved Baseline | Reason | Comment |
---|---|---|---|---|---|
7240 | 12/28/2011 | Correction | Correction to measurement condition from over to under. Changed contract to omit sync since this is becoming a non-major. | ||
2114 | 10/27/2010 | 04/14/2012 | 6.29 | Rebaseline - other | IT Dashboard version of investment is missing one milestone. |
6711 | 07/26/2011 | 04/14/2012 | 5.29 | Correction | Correction. |
6142 | 06/22/2011 | 04/14/2012 | 4.51 | Correction | Correction. |
6143 | 06/22/2011 | 04/14/2012 | 5.11 | Correction | Correction |
3790 | 03/22/2011 | 04/14/2012 | 7.27 | Replan - planned change with minimal change in overall scope, cost or schedule objectives | Updated Milestone. |
3730 | 02/28/2011 | 04/14/2012 | 7.20 | Correction | correction |
3732 | 02/28/2011 | 04/14/2012 | 7.27 | Rebaseline - adding new iteration | add one milestone |
3624 | 02/25/2011 | 04/14/2012 | 7.20 | Correction | This is a correction |
3634 | 02/25/2011 | 04/14/2012 | 7.20 | Correction | Updated milestone. |
3640 | 02/25/2011 | 04/14/2012 | 7.20 | Rebaseline - adding new iteration | new iteration |
3728 | 02/25/2011 | 04/14/2012 | 7.20 | Correction | correction |