An Official Website of the United States Government

Saturday, September 15, 2012

Login

Data is current as of August 31, 2012. Updated data will be available following the September-October period and will reflect updates made during that period.

   

Investment Summary

UPI: 009-000001367

The Investment was Downgrade in the Budget Year 2013 Exhibit 53 submission on 05/03/2012.

FY12 Exhibit 300

For the displayed Eliminated/ Downgraded investment, the summary below provides last reported snapshot of the particular investment in IT Dashboard. This summary displays a chart reflecting Overall Rating over time, clearly identifying specific activities such as rebaseline events and last reported cost and schedule ratings and Evaluation by Agency CIO. A tabular history of major events is also available at the bottom of the page.

Final Overall Rating: 9.4
Final Cost Rating: 8.9
Final Schedule Rating: 9.5
Final Evaluation: 5 out of 5
Tabular Data
Rated Date Overall Rating Cost Rating Schedule Rating CIO Evaluation
2009-06-30 10 10 10
2009-08-01 7.5 10 10 4
2009-08-19 7.5 10 10 4
2009-09-01 7.5 10 10 4
2009-09-30 7.5 10 10 4
2009-10-01 7.5 10 10 4
2009-11-01 7.5 10 10 4
2009-12-01 7.5 10 10 4
2010-01-01 7.5 10 10 4
2010-02-01 7.5 10 10 4
2010-03-01 7.5 10 10 4
2010-03-17 10 10 10 5
2010-04-01 10 10 10 5
2010-05-01 10 10 10 5
2010-06-01 9.6 8.9 9.9 5
2010-06-23 9.6 8.9 9.9 5
2010-07-01 9.6 8.9 9.9 5
2010-07-23 9.5 8.9 9.7 5
2010-08-01 9.5 8.9 9.7 5
2010-08-19 9.6 8.9 9.9 5
2010-09-01 9.6 8.9 9.9 5
2010-10-01 9.6 8.9 9.9 5
2010-10-29 8.3 6 9.1 5
2010-11-01 8.3 6 9 5
2010-11-08 8.4 6.4 8.8 5
2010-11-30 9.5 8.9 9.6 5
2010-12-01 9.5 8.9 9.6 5
2011-01-01 9.5 8.9 9.6 5
2011-02-01 9.5 8.9 9.6 5
2011-02-24 9.5 8.9 9.6 5
2011-03-01 9.5 8.9 9.6 5
2011-03-31 9.5 8.9 9.5 5
2011-04-01 9.5 8.9 9.5 5
2011-04-29 9.5 8.9 9.7 5
2011-05-01 9.5 8.9 9.7 5
2011-05-31 9.6 9 9.7 5
2011-06-01 9.6 9 9.7 5
2011-06-30 9.5 9 9.5 5
2011-07-01 9.5 9 9.5 5
2011-07-28 9.4 8.9 9.5 5
2011-08-01 9.4 8.9 9.5 5
2011-09-01 9.4 8.9 9.5 5
2011-09-06 9.4 8.9 9.5 5
Rebaseline Events
Baseline Event # Baseline Event Date Planned Completion Date Life cycle costs of Approved Baseline Reason Comment
275 09/30/2009 09/30/2011 3.39 Internal - Inaccurate Baseline
3231 08/10/2010 09/30/2014 13.07 Rebaseline - other This Rebaseline appends Performance Metrics to the approved budget through FY 2014. It was previously anticipated that ICE would be replaced by the system selected under the HHS Consolidation of Acquisition Systems initiatives during FY 2007 – FY 2010. However, that planning assumption was negated, so expenditures for ICE were extended through FY 2014. This correction addresses metrics for essential enhancements, continuing operations, through disposition in FY 2014.
870 08/09/2010 09/30/2014 12.87 Internal - Technological Change It was previously anticipated that ICE would be replaced by the system selected under the HHS Consolidation of Acquisition Systems initiatives during FY 2007 – FY 2010. However, that planning assumption has been negated, so expenditures for ICE must be extended through FY2014. The additional funding addresses essential enhancements, continuing operations, disposition, and the anticipated migration to the future HHS solution by FY 2014.