LoginFor the displayed Eliminated/ Downgraded investment, the summary below provides last reported snapshot of the particular investment in IT Dashboard. This summary displays a chart reflecting Overall Rating over time, clearly identifying specific activities such as rebaseline events and last reported cost and schedule ratings and Evaluation by Agency CIO. A tabular history of major events is also available at the bottom of the page.
Rated Date | Overall Rating | Cost Rating | Schedule Rating | CIO Evaluation |
---|---|---|---|---|
2009-06-30 | 10 | 10 | 10 | |
2009-08-01 | 10 | 10 | 10 | 5 |
2009-09-01 | 10 | 10 | 10 | 5 |
2009-10-01 | 10 | 10 | 10 | 5 |
2009-11-01 | 10 | 10 | 10 | 5 |
2009-12-01 | 10 | 10 | 10 | 5 |
2010-01-01 | 8.3 | 10 | 5 | 5 |
2010-01-12 | 8.3 | 10 | 5 | 5 |
2010-02-01 | 10 | 10 | 10 | 5 |
2010-03-01 | 10 | 10 | 10 | 5 |
2010-04-01 | 10 | 10 | 10 | 5 |
2010-04-16 | 10 | 10 | 10 | 5 |
2010-05-01 | 10 | 10 | 10 | 5 |
2010-06-01 | 9.9 | 9.8 | 10 | 5 |
2010-06-15 | 9.9 | 9.8 | 10 | 5 |
2010-07-01 | 9.9 | 9.8 | 10 | 5 |
2010-07-15 | 9.9 | 9.8 | 10 | 5 |
2010-08-01 | 9.9 | 9.8 | 10 | 5 |
2010-08-11 | 9.9 | 9.8 | 10 | 5 |
2010-09-01 | 9.9 | 9.8 | 10 | 5 |
2010-09-16 | 9.9 | 9.9 | 9.9 | 5 |
2010-10-01 | 9.9 | 9.9 | 9.9 | 5 |
2010-10-14 | 8.9 | 6.9 | 9.8 | 5 |
2010-11-01 | 8.8 | 6.9 | 9.5 | 5 |
2010-11-15 | 9.9 | 9.6 | 10 | 5 |
2010-12-01 | 9.9 | 9.6 | 10 | 5 |
2010-12-16 | 9.9 | 9.6 | 10 | 5 |
2011-01-01 | 9.9 | 9.6 | 10 | 5 |
2011-01-14 | 9.9 | 9.6 | 10 | 5 |
2011-02-01 | 9.9 | 9.6 | 10 | 5 |
2011-02-24 | 9.9 | 9.6 | 9.9 | 5 |
2011-03-01 | 9.9 | 9.6 | 10 | 5 |
2011-04-01 | 9.9 | 9.6 | 10 | 5 |
2011-04-13 | 9.9 | 9.7 | 9.9 | 5 |
2011-05-01 | 9.9 | 9.7 | 9.9 | 5 |
2011-05-13 | 9.7 | 9.5 | 9.6 | 5 |
2011-06-01 | 9.7 | 9.5 | 9.6 | 5 |
2011-06-15 | 9.8 | 9.6 | 9.9 | 5 |
2011-07-01 | 9.8 | 9.6 | 9.9 | 5 |
2011-07-13 | 9.8 | 9.6 | 9.8 | 5 |
2011-08-01 | 9.8 | 9.6 | 9.8 | 5 |
2011-09-01 | 9.8 | 9.6 | 9.8 | 5 |
2011-09-06 | 9.8 | 9.6 | 9.8 | 5 |
Baseline Event # | Baseline Event Date | Planned Completion Date | Life cycle costs of Approved Baseline | Reason | Comment |
---|---|---|---|---|---|
1265 | 09/13/2010 | 09/30/2019 | 133.33 | Rebaseline - other | Adding milestones for out year planning. |
3214 | 01/31/2011 | 09/30/2019 | 133.33 | Rebaseline - other | This is a PRM rebaseline to address changes in the 'ratings' column as well as to correct previously entered erroneous data in the wrong column. |