Investment Summary

UPI: 012-000001020

The Investment was Downgrade in the Budget Year 2013 Exhibit 53 submission on 05/02/2012.

FY12 Exhibit 300

For the displayed Eliminated/ Downgraded investment, the summary below provides last reported snapshot of the particular investment in IT Dashboard. This summary displays a chart reflecting Overall Rating over time, clearly identifying specific activities such as rebaseline events and last reported cost and schedule ratings and Evaluation by Agency CIO. A tabular history of major events is also available at the bottom of the page.

Final Overall Rating: 9.8
Final Cost Rating: 9.6
Final Schedule Rating: 9.8
Final Evaluation: 5 out of 5
Tabular Data
Rated Date Overall Rating Cost Rating Schedule Rating CIO Evaluation
2009-06-30 10 10 10
2009-08-01 10 10 10 5
2009-09-01 10 10 10 5
2009-10-01 10 10 10 5
2009-11-01 10 10 10 5
2009-12-01 10 10 10 5
2010-01-01 8.3 10 5 5
2010-01-12 8.3 10 5 5
2010-02-01 10 10 10 5
2010-03-01 10 10 10 5
2010-04-01 10 10 10 5
2010-04-16 10 10 10 5
2010-05-01 10 10 10 5
2010-06-01 9.9 9.8 10 5
2010-06-15 9.9 9.8 10 5
2010-07-01 9.9 9.8 10 5
2010-07-15 9.9 9.8 10 5
2010-08-01 9.9 9.8 10 5
2010-08-11 9.9 9.8 10 5
2010-09-01 9.9 9.8 10 5
2010-09-16 9.9 9.9 9.9 5
2010-10-01 9.9 9.9 9.9 5
2010-10-14 8.9 6.9 9.8 5
2010-11-01 8.8 6.9 9.5 5
2010-11-15 9.9 9.6 10 5
2010-12-01 9.9 9.6 10 5
2010-12-16 9.9 9.6 10 5
2011-01-01 9.9 9.6 10 5
2011-01-14 9.9 9.6 10 5
2011-02-01 9.9 9.6 10 5
2011-02-24 9.9 9.6 9.9 5
2011-03-01 9.9 9.6 10 5
2011-04-01 9.9 9.6 10 5
2011-04-13 9.9 9.7 9.9 5
2011-05-01 9.9 9.7 9.9 5
2011-05-13 9.7 9.5 9.6 5
2011-06-01 9.7 9.5 9.6 5
2011-06-15 9.8 9.6 9.9 5
2011-07-01 9.8 9.6 9.9 5
2011-07-13 9.8 9.6 9.8 5
2011-08-01 9.8 9.6 9.8 5
2011-09-01 9.8 9.6 9.8 5
2011-09-06 9.8 9.6 9.8 5
Rebaseline Events
Baseline Event # Baseline Event Date Planned Completion Date Life cycle costs of Approved Baseline Reason Comment
1265 09/13/2010 09/30/2019 133.33 Rebaseline - other Adding milestones for out year planning.
3214 01/31/2011 09/30/2019 133.33 Rebaseline - other This is a PRM rebaseline to address changes in the 'ratings' column as well as to correct previously entered erroneous data in the wrong column.