Investment Summary

UPI: 009-38-01-06-01-1010-00

The Investment was Eliminated by omission in the Budget Year 2013 Exhibit 53 submission on 05/03/2012.

FY12 Exhibit 300

For the displayed Eliminated/ Downgraded investment, the summary below provides last reported snapshot of the particular investment in IT Dashboard. This summary displays a chart reflecting Overall Rating over time, clearly identifying specific activities such as rebaseline events and last reported cost and schedule ratings and Evaluation by Agency CIO. A tabular history of major events is also available at the bottom of the page.

Final Overall Rating: 7.5
Final Cost Rating: 9.9
Final Schedule Rating: 10
Final Evaluation: 4 out of 5
Tabular Data
Rated Date Overall Rating Cost Rating Schedule Rating CIO Evaluation
2009-06-30 10 10 10
2009-08-01 10 10 10 5
2009-09-01 10 10 10 5
2009-09-24 10 10 10 5
2009-10-01 10 10 10 5
2009-11-01 10 10 10 5
2009-12-01 10 10 10 5
2010-01-01 10 10 10 5
2010-02-01 10 10 10 5
2010-02-17 10 10 10 5
2010-03-01 10 10 10 5
2010-03-17 7.5 10 10 4
2010-04-01 7.5 10 10 4
2010-05-01 7.5 10 10 4
2010-06-01 7.5 9.9 10 4
2010-07-01 7.5 9.9 10 4
2010-08-01 7.5 9.9 10 4
2010-08-19 5 9.9 10 3
2010-09-01 5 9.9 10 3
2010-10-01 5 9.9 10 3
2010-11-01 5 5.8 9.8 3
2010-11-08 5 6.4 9.7 3
2010-12-01 5 9.6 10 3
2011-01-01 5 9.6 10 3
2011-02-01 5 8.9 10 3
2011-02-25 7.5 8.5 10 4
2011-03-01 7.5 8.5 10 4
2011-04-01 7.5 8.2 10 4
2011-05-01 7.5 9.9 10 4
2011-06-01 7.5 9.9 10 4
2011-06-30 8.2 7.1 10 4
2011-07-01 8.2 7.1 10 4
2011-07-28 7.5 9.9 10 4
2011-08-01 7.5 9.9 10 4
2011-09-01 7.5 9.9 10 4
2011-09-06 7.5 9.9 10 4
Rebaseline Events
Baseline Event # Baseline Event Date Planned Completion Date Life cycle costs of Approved Baseline Reason Comment
2268 11/08/2010 09/30/2015 236.95 Correction Correction to completed milestones required because of reporting system error -- Did not include actual cost in initial October update.
177 09/24/2009 09/30/2011 107.94 Internal - Inaccurate Baseline
434 01/29/2010 09/30/2015 178.02 Internal - Other