An Official Website of the United States Government

Saturday, September 15, 2012

Login

Data is current as of August 31, 2012. Updated data will be available following the September-October period and will reflect updates made during that period.

   

Investment Summary

UPI: 024-000005112

The Investment was Eliminated by funding in the Budget Year 2013 Exhibit 53 submission on 05/03/2012.

FY12 Exhibit 300

For the displayed Eliminated/ Downgraded investment, the summary below provides last reported snapshot of the particular investment in IT Dashboard. This summary displays a chart reflecting Overall Rating over time, clearly identifying specific activities such as rebaseline events and last reported cost and schedule ratings and Evaluation by Agency CIO. A tabular history of major events is also available at the bottom of the page.

Final Overall Rating: 5
Final Cost Rating: 9.8
Final Schedule Rating: 10
Final Evaluation: 3 out of 5
Tabular Data
Rated Date Overall Rating Cost Rating Schedule Rating CIO Evaluation
2009-06-30 10 10 10
2009-08-01 7.5 10 10 4
2009-08-27 7.5 10 10 4
2009-09-01 7.5 10 10 4
2009-10-01 7.5 10 10 4
2009-11-01 7.5 10 10 4
2009-12-01 7.5 10 10 4
2010-01-01 7.5 10 10 4
2010-02-01 7.5 10 10 4
2010-03-01 5 10 10 3
2010-04-01 5 10 10 3
2010-04-29 5 10 10 3
2010-05-01 5 10 10 3
2010-06-01 5 6 7.7 3
2010-07-01 5 6.4 7.4 3
2010-08-01 5 6.8 7 3
2010-08-05 5 9.8 10 3
2010-09-01 5 9.8 10 3
2010-10-01 5 9.8 10 3
2010-11-01 5 9.7 9.8 3
2010-12-01 5 9.8 10 3
2011-01-01 5 9.8 10 3
2011-02-01 5 8.3 9.7 3
2011-02-22 5 9.8 10 3
2011-03-01 5 9.8 10 3
2011-04-01 5 9.8 10 3
2011-05-01 5 9.8 10 3
2011-06-01 5 9.8 10 3
2011-07-01 5 9.8 10 3
2011-08-01 5 9.8 10 3
2011-09-01 5 9.8 10 3
2011-09-06 5 9.8 10 3
Rebaseline Events
Baseline Event # Baseline Event Date Planned Completion Date Life cycle costs of Approved Baseline Reason Comment
823 08/05/2010 12/31/2016 101.91 Internal - Other SFI cost and schedule milestones were re-planned without changing budget authority to align with reduced funding and decommissioning of pilot deployment sites. Milestones up to FY 2016 were adjusted to reflect a lower FTE requirement needed to support reduced deployments and maintain basic O&M support. Milestones were added for FY 2016 consistent with onging requirement for cargo scanning at foreign ports where SFI is deployed.
3061 01/06/2011 12/31/2016 107.96 Rebaseline - other SFI cost and schedule milestones were updated to align with reduced funding and decommissioning of pilot deployment sites.