AREA(S) AFFECTED:
 Location: Maryland Bethesda Main Campus
 Building: 33
 Rooms/Area(s): This will be done in 1S04 and will affect the north side of the building the Fire pump normal power and MCB1 the fire pump and MCB1 will have no affect on the buildings occupants there will also be 2 spare breakers done and a ETCB1

UTILITIES AFFECTED:
 Electricity

DATES:
 Begin:   Saturday, January 26, 2013 -- 6:00:00 AM
 End:      Saturday, January 26, 2013 -- 7:00:00 PM

DETAILS:
 Purpose of Shutdown - Replace trip units for main breakers in the electrical vault

 Extent of Shutdown - This will be to replace the trip units on the north bus duct and other breakers there will be NO NORMAL POWER on the NORTH side of the building from 1W10 TO 1N01 from 1E13 TO 1W03, 1E14 TO 1E08, 2W10 T0 2N01,2E14 TO 2E08, 2E13 TO 2W03, 3W10 TO 3N01, 3E14 TO 3E08, 3E13 TO 3W03 anything that is NOT PLUGGED into a RED outlet WILL NOT HAVE POWER FOR 2 HOURS from 8am to 10am.This will also affect the cold boxes on this side of the building during this shutdown.In the Vivarium it will be from BN06 TO BW01F This will also affect the microscopes on BE11. There will be a breaker done every 2 hours until 6pm we will then perform a generator test to prove the breakers are working correctly.It will be approx. 2 hours per breaker.

 Additional Remarks - Electrical shutdown to replace trip units on vault breakers



If you need further information, contact:  (301)435-8000 Central Call Desk

Note: This form was generated by the ORFDO Utility Shutdown Notification System.
For additional information or to receive future notifications regarding your building please visit
http://orf2.od.nih.gov/utilityshutdown/scripts/index.asp