AREA(S) AFFECTED:
Location: Maryland Bethesda Main Campus
Building: 6
Rooms/Area(s): All areas fed by the emergency power riserUTILITIES AFFECTED:
Electricity
DATES:
Begin: Wednesday, February 13, 2013 -- 6:00:00 AM
End: Wednesday, February 13, 2013 -- 7:00:00 AM
DETAILS:
Purpose of Shutdown - Perform quarterly emergency power generator transfer test Bldg 6; Fac # 10939
Extent of Shutdown - Wherever the emergency electricity is provided
Additional Remarks - It will affect to wherever the emergency electricity provides. Momentary switches from PEPCO power to emergency generator power and vies versa.
If you need further information, contact: (301)435-8000 Central Call Desk
Note: This form was generated by the ORFDO Utility Shutdown Notification System.
For additional information or to receive future notifications regarding your building please visit
http://orf2.od.nih.gov/utilityshutdown/scripts/index.asp