Spent Fuel Pools

The water-pool option involves storing spent fuel assemblies under at least 20 feet of water, which provides adequate shielding from the radiation for anyone near the pool. The assemblies are moved into the water pools from the reactor along the bottom of water canals, so that the spent fuel is always shielded to protect workers.

About one-fourth to one-third of the total fuel load from the pools is spent and removed from the reactor every 12 to 18 months and replaced with fresh fuel.

Current regulations permit re-racking of the spent fuel pool grid and fuel assembly consolidation, subject to NRC review and approval, to increase the amount of spent fuel that can be stored in the pool. Both of these methods are constrained by the size of the pool.

Page Last Reviewed/Updated Friday, December 21, 2012