Audits

 

Initial Link of Seattle Central Link Light Rail Project

July 07, 2003
 
 
 

Summary

We publicly released our report on the Initial Segment of the Seattle Central Link Light Rail Project, in response to a 2002 request from the former Chairman of the House Transportation Appropriations Subcommittee. We found: Sound Transit has significantly strengthened its proposal for constructing the project’s first segment; the Federal Transit Administration (FTA) has provided strong oversight of Sound Transit’s plans; project cost, schedule, and funding appear to be reasonable; Sound Transit has adequately addressed the safety issues related to operating buses and trains in the tunnel; and FTA’s requirements for a stand alone system have been met. We recommended that alternative local revenues be committed to the project in case of a funding deficit or shortfall and amendment of the finance plan accordingly. FTA agreed with our recommendation.

.